Project Updates: Master Plans and Studies
Posted on: March 25, 2025[ARCHIVED] Master Plans and Studies Project Updates - Week of March 24, 2025
Master Plans and Studies Project Updates - Week of March 24, 2025
Facilities Master Plan
- March 25, 2025 – Updated schedule to complete will be sent to the City by the end of this week. HDR has started work on a feasibility study for a building on Edmond street in consideration for new Public Works, Utility Maintenance, and Fleet facility.
Sidewalk, Bikes, Trails Master Plan and ADA Transition Plan
- March 25, 2025 – Parks and trails are done for ADA analysis. Working on north side of downtown. Existing conditions analysis should be done this week.
Water Supply Evaluation
W/WW/WWTP Master Plan
- Still working on scope and fees. Presenting at the EDC board meeting tomorrow for approval. WWTP plan will follow W/WW plan as it will inform demands and loading.