Project Updates: Facilities
Posted on: March 18, 2025[ARCHIVED] Facilities Project Updates - Week of March 17, 2025
Facilities Project Updates - Week of March 17, 2025
Justice Center
- March 4, 2025 – HDR is working on documentation for 2nd Street closure and abandonment. Working with local business owners to reroute truck delivery traffic around the Justice Center. Utility removals are ongoing.
Cemetery Office Building
- March 4, 2025 – Working through cultural resources requirements from the Texas Historical Commission.
Backup Generators for Critical Facilities
- March 11, 2025 – The Animal Shelter will be completed today. City Hall will be done in 2 phases to reduce possibility for outage during work hours on Friday the 21st and Friday the 28th.
Airport Ramp Reconstruction
- March 11, 2025 – Phase 4 of the airport ramp reconstruction is fully milled and limed.
Airport Fuel Farm Construction (Complete)
- Project Complete - A ribbon cutting will be scheduled soon.
Fire Stations 1 and 2 Renovation
- March 11, 2025 – Final plans have been delivered. Cost estimates are under review.